Westenergie supplies over 6.6 million people in North Rhine-Westphalia, Rhineland-Palatinate and Lower Saxony with electricity, gas and water every day – they all depend on a permanently secure supply. This is why Westenergie has been relying on ESP‘s highly stable satellite solutions for the remote monitoring and control of critical infrastructures such as substations and wind farms since 2008.
The Saarbrücken-based company provides the customer with a serial SCADA end-to-end connection (IEC 60870-5-101) via satellite and also supplies a dashboard that enables the customer to closely monitor the status of their systems.
As in all technical systems and installations, wear and tear along with technological innovations in satellite technology make it necessary to sooner or later migrate entire systems. “The reason for the hub migration at Westenergie is the switch to the next generation of teleports and new geostationary satellites. The current satellite period is due to expire soon,” explains Thomas Maul, CEO of ESP. “This is a quite normal process – hubs and satellites have a very long life expectancy, but after over 10 years they simply have to be replaced. However, in order for the interaction with the new satellite to function properly in the future, the hub and all field stations must also be migrated.”
The hub is something like the centerpiece for communication with the satellite. A migration during ongoing operations is tantamount to open-heart surgery and requires long and precise preparation: planning, link budget, training, network concept and procurement took only a few months in this case, despite everything. ESP now operates the systems on its own ESP Europe1 satellite transponder.
A particular challenge: hundreds of field stations had to be integrated into the new hub and the new network structure during ongoing operations. Subsequently, the modified API interface for the customer dashboard was implemented. The new hub is managed exclusively by ESP. “We carried out the switchover in a very orderly process together with Westenergie, remotely from Saarbrücken,” says Julius Schaad, Project Manager with overall responsibility, describing the process and once again emphasizing the good and close cooperation with the customer. “Westenergie‘s control center determined which systems could be migrated and at what time, and we then implemented this. It went hand in hand.”
Julius Schaad, Project Manager